November 2006
City of Manvel development application submitted
Draft Planned Unit Development for each city submitted
Conceptual Master Plan approved by Brazoria County Drainage District #3
December 2006
Municipal Utility District (MUD) creation petitions submitted to cities (expected consideration Manvel 01/08/2007,
Iowa Colony 01/15/2007
MUD creation reports completed
Traffic Impact Analysis completed
Draft master water and swere plan completed
HOA and deed restriction attorney engaged; draft deed restrictions received
January 2007
Manvel zone change request submitted
MUD boundries determined
Draft development agreements for each city prepared
Final master drianage plan in progress
Seven Oaks Parkway Preliminary Engineering Review in progress
Final master drainage plan in progress
Wetlands delineation for Phase I completed
Wastewater discharge permit (Iowa Colony) "administratively complete"
State Highway 288 overpass coordination with Sterling Lakes and Texas Department of Transportation initiated
Preliminary monumentation planning in progress
Preliminary private utility coordination initiated; marketing agreements in progress
Investigation alternative delivery methods for phone, cable, data, and security
Pipeline, railroad, and canal coordination initiated
Cities to consider one initial director for each utility district